A New Model for Healthcare Delivery

Healthcare infrastructure is among the most complex building types to design and deliver. Hospitals must simultaneously support patient care, advanced medical technologies, research, and long-term operational efficiency—often within tight timelines, constrained sites, and evolving regulatory environments. As healthcare systems across North America seek to modernize aging facilities, the challenge is no longer simply how to build hospitals, but how to build them smarter, faster, and more resiliently.

The New St. Paul’s Hospital project in Vancouver, British Columbia, represents a step change in how large-scale healthcare infrastructure can be delivered. Designed as a digitally integrated, patient-focused acute-care and research campus, the $1.7 billion facility is scheduled to open in 2027 and will comprise more than 5,500 rooms across a 2 million-square-foot footprint. Beyond its scale, the project sets a new benchmark for technology-enabled collaboration, demonstrating how digital integration can fundamentally transform project delivery and outcomes.

‍

Complexity at an Unprecedented Scale

Awarded as a design-build contract to PCL Constructors Westcoast Inc. in 2021, the New St. Paul’s Hospital project launched during one of the most volatile periods in recent construction history. The team was tasked with delivering an exceptionally complex facility under aggressive timelines, while navigating the final stages of a global pandemic, hyper-escalation, and ongoing supply chain instability driven by geopolitical disruption and material shortages.

Healthcare projects already demand heightened levels of coordination due to stringent clinical requirements, intensive building systems, and extensive stakeholder engagement. In this case, those demands were amplified by the hospital’s ambition to integrate patient care, research, sustainability, and cultural inclusivity into a single, future-ready campus.

Traditional delivery methods—reliant on fragmented documentation, linear coordination, and manual tracking—would have struggled under these conditions. Meeting the project’s objectives required a fundamentally different approach to coordination, information management, and decision-making.

‍

Digital Integration as a Strategic Foundation

From the outset, the project team made a deliberate decision to anchor delivery around Building Information Modeling (BIM), not as a visualization tool, but as the central nervous system of the project. A robust BIM execution plan established the digital models as the single source of truth, aligning design, construction, and future operations within a shared data environment.

This BIM-centric strategy allowed all disciplines to operate from coordinated, federated models, significantly reducing information silos and enabling real-time collaboration. Rather than layering technology as an afterthought, digital tools were intentionally integrated to extend the value of the models across the project lifecycle.

Platforms such as Revizto enabled multidisciplinary teams to conduct clash detection, issue tracking, and design coordination directly within the 3D environment. Scheduling data was linked to BIM through production trackers, providing real-time visibility into progress versus plan and enabling proactive management of risks and constraints. Quality and inspection workflows were digitized through BIM 360 Build, directly associating field observations with model elements for greater accountability and traceability.

‍

Bridging the Gap Between Model and Field

A defining feature of the New St. Paul’s Hospital project was its ability to connect digital intent with physical execution. Drone mapping technologies, integrated with layout tools such as HP SitePrint, translated design data directly into site activities, improving layout accuracy and reducing rework.

Reality capture platforms, including DroneDeploy and Cupix, added an immersive layer to construction monitoring. High-resolution aerial imagery and 3D site captures enabled automated progress tracking, remote inspections, and as-built comparisons against design models. This proved particularly valuable for coordinating with off-site stakeholders and maintaining alignment across a large, fast-moving project.

Immersive technologies further enhanced decision-making. Virtual reality mock-ups allowed clinicians and end-users to experience surgical suites and patient spaces before construction, facilitating early validation and refinement. Mixed reality tools enabled model overlays in physical spaces, supporting layout verification and constructability reviews in real time.

Each of these technologies delivered value independently, but their true impact emerged through integration—stacking spatial, temporal, and qualitative data back into the BIM environment to create a holistic, decision-rich project ecosystem.

‍

Innovation Through Smart Workflows and Connected Data

Beyond individual tools, the project introduced smart workflows designed to make construction more data-aware and responsive. Autodesk Construction Cloud (ACC) served as the central collaboration hub, supporting document control, model coordination, issue management, and asset data collection.

PCL’s Job Site Solutions (JSx) further extended digital capability into field operations. By integrating IoT-enabled Job Site Insights® sensors, the team gained real-time visibility into site conditions, safety risks, security, and resource utilization. These insights supported better planning, improved productivity, and enhanced risk mitigation—critical on a project of this scale.

The integration of open Application Programming Interfaces (APIs)  and data connectors enabled seamless information flow across platforms, reducing manual data entry and minimizing errors. Reporting and analytics tools such as Microsoft Power BI aggregated data from multiple sources, transforming raw project information into actionable dashboards that supported leadership-level decision-making.

‍

Measurable Outcomes and Operational Gains

The impact of this digitally integrated approach is evident in a series of measurable results achieved throughout the project:

  • Virtual reality simulations of complex surgical suites eliminated an entire round of user group meetings, saving an estimated three months in design time.
  • Architecturally significant equipment mock-ups, self-performed by PCL using timber replicas, significantly reduced validation costs while meeting clinical requirements.
  • Automated room status tracking, integrating BIM 360, Primavera P6, and Excel macros, reduced manual tracking from days to under ten minutes and enabled real-time Power BI dashboards.
  • Streamlined quality inspections through consolidated BIM-based drawings significantly reduced inspection time and minimized rework.
  • Geotechnical visualization overlaying MASW test data with structural models ensured optimal foundation placement and reduced excavation risk.
  • Integrated production tracking unified design, schedule, and field data into a single dashboard, improving forecasting accuracy and coordination across the entire facility.

Together, these outcomes demonstrate how digital integration can move beyond efficiency gains to fundamentally reshape how complex healthcare projects are delivered.

‍

Interoperability as an Enabler of Collaboration

A critical enabler of success on the New St. Paul’s Hospital project was its commitment to open standards and interoperability. The use of APIs and plugins allowed seamless data exchange between platforms such as Autodesk Revit, Navisworks, Revizto, and Cupix, ensuring consistency and accuracy without vendor lock-in.

COBie standards were employed to structure asset and facility management data for handover, ensuring that information generated during design and construction could be directly leveraged during operations. This approach reinforces a lifecycle mindset, where digital delivery supports long-term performance rather than ending at substantial completion.

By prioritizing interoperable systems, the project team was able to select best-in-class tools while maintaining a unified digital ecosystem—reducing silos and enabling true collaboration.

‍

Setting a New Benchmark for Industry Practice

The workflows developed on this project extend far beyond healthcare. Early and continuous engagement of clients and operators through accessible digital tools allowed meaningful feedback to shape decisions when changes were least costly. This shift from reactive coordination to proactive collaboration represents a significant evolution in industry practice.

Equally important is the integration of asset data and operational intelligence into the delivery process. By treating digital models as long-term resources rather than short-term construction tools, the project reframes success around lifecycle value rather than project completion alone.

These practices offer a scalable blueprint for commercial, institutional, and infrastructure projects seeking greater transparency, efficiency, and stakeholder alignment.

‍

Economic and Social Value Creation

At its peak, the project employed more than 2,000 site workers daily with over 10,000 site workers cycling through the life cycle of the project, generating substantial economic activity within British Columbia. The use of local vendors and subcontractors amplified this impact by strengthening regional supply chains and supporting small and medium-sized businesses.

Beyond construction, the hospital will deliver long-term economic benefits through improved healthcare outcomes, reduced system costs, and the creation of permanent jobs in healthcare, research, administration, and facility operations. A healthier population contributes directly to productivity and economic resilience.

The project also aligns with broader social objectives. Targeting LEED certification, it advances environmental sustainability through energy efficiency, emissions reduction, and healthy indoor environments. Compliance with the City of Vancouver’s Community Benefits Agreement ensures local hiring, workforce diversity, and inclusive economic opportunities—embedding social value into project delivery.

‍

A Blueprint for Future-Ready Infrastructure

The New St. Paul’s Hospital project demonstrates how digitally integrated delivery can redefine what is possible in healthcare infrastructure. By placing BIM at the centre of a connected ecosystem of technologies, the project transformed complexity into clarity and coordination into capability.

More than a single success story, it offers a replicable model for how the Architecture, Engineering, Construction, Owners and Operators (AECOO) industry can respond to rising complexity, tighter timelines, and growing societal expectations. As healthcare systems and public infrastructure continue to evolve, this approach provides a pathway to deliver facilities that are not only technically advanced, but economically resilient, socially inclusive, and operationally sustainable.

In doing so, New St. Paul’s Hospital sets a new standard for how we design, build, and ultimately care for the communities our buildings serve.