The Persistent Risk at the Heart of Construction
Despite decades of innovation in construction methods and equipment, crane operations remain one of the most significant sources of risk on job sites. Suspended loads, wind exposure, limited visibility, and congested working conditions continue to place workers in vulnerable positions. Regulators consistently cite uncontrolled or spinning loads as a leading cause of serious injuries and near misses—an issue that becomes more pronounced as projects grow taller, denser, and more complex.
At the same time, modern construction demands greater speed and precision than ever before. Urban density, infrastructure renewal, and population growth are pushing project teams to build in tighter footprints and under increasingly compressed schedules. These conditions expose the limitations of traditional load-control methods, which rely heavily on manual taglines and workers physically managing loads that can weigh ten to twenty times more than a person.
The McCarrons Water Treatment Plant project in Saint Paul, Minnesota, presented a real-world test case for addressing these intersecting pressures. Faced with high-risk lifts in confined, wind-affected conditions, PCL Construction partnered with Vita Industrial to explore whether semi-autonomous lifting technology could meaningfully improve safety and performance.
When Precision Becomes Non-Negotiable
The specific challenge at McCarrons involved lifting and placing large formwork panels—each measuring approximately 25’ by 25’ and weighing close to 10,000 pounds—into a subterranean structure. The panels’ large surface area made them particularly susceptible to wind, causing rotation and instability during lifts.
Compounding this risk was the extreme tolerance required for placement. Panels had to be lowered into position with only two inches of clearance on either side, threading between rebar struts within the excavation. Under conventional methods, this required multiple workers positioned inside the structure to manually guide and control the load as it descended.
This approach placed crews directly in harm’s way, exposed to pinch points, struck-by hazards, and uncontrolled movement—while also slowing operations and increasing the likelihood of delays due to wind conditions. Precision, safety, and productivity were all under strain, highlighting the need for a fundamentally different lifting strategy.
Rethinking Load Control as a System
Rather than attempting to further mitigate risk through incremental procedural changes, PCL and Vita Industrial approached the problem as a system-level challenge. The question was not how to better manage traditional taglines, but how to remove the need for them altogether.
The answer came in the form of the Vita Load Navigator (VLN), a semi-autonomous crane lifting device designed to stabilize and orient loads without manual intervention. Installed below the crane hook, the VLN integrates propulsion-driven thrusters into a spreader beam and is controlled remotely by an operator on the ground.
By continuously measuring more than 1,000 data points per second—including position, motion, load behavior, and environmental conditions—the VLN actively counters rotation, spinning, and drift. The system enables operators to rotate loads on demand, hold a fixed heading using GPS-based Position Hold (even in winds up to 30 mph), and record precise geo-locations for repetitive lifts.
This shift reframed crane operations from reactive control to proactive, digitally assisted precision.
From Manual Intervention to Semi-Autonomous Execution
Once deployed on site, the VLN immediately changed how work was executed. The number of workers required inside the excavation during lifts was reduced from three to one, dramatically decreasing exposure to high-risk conditions. Manual taglines were much less frequently used, removing a long-standing source of strain and hazard.
The VLN’s Position Hold capability proved especially valuable. Even in windy conditions that would normally halt lifting operations, crews were able to maintain control and place panels accurately within inches of their intended position. This stability reduced rework, prevented damage, and eliminated wind-related delays that frequently disrupt crane-dependent scopes.
In addition, the VLN’s Memory Function allowed operators to pre-program lift paths and set points for repetitive operations. What had previously taken approximately 20 minutes per lift was reduced to roughly five minutes, transforming crane work from a bottleneck into a predictable, repeatable process.
Performance Measured in Safety and Productivity
PCL Construction trialed the Vita Load Navigator over a 30-day period at the McCarrons Water Treatment Plant. The results demonstrated tangible gains across safety, schedule, and cost metrics.
From a safety perspective, the VLN enabled total load stabilization, eliminating uncontrolled movement and significantly reducing exposure to pinch points and struck-by hazards. Crews were able to operate safely in wind speeds of up to 30 mph—conditions that would typically force shutdowns.
Productivity improvements were equally compelling. By allowing work to continue during adverse conditions, the project avoided two full days of weather-related delays, saving approximately 100 worker-hours. Efficiency gains during normal operations further reduced labor demands.
The scope’s budgeted productivity rate was 0.085 hours per square foot, with typical performance around 0.075. With the VLN in use, final productivity reached 0.0485 hours per square foot—an improvement of roughly 35 percent. In total, the project saved approximately 250 worker-hours, translating to an estimated $23,000 in direct labor cost savings over the trial period.
These results were achieved using a rental unit, with typical monthly costs ranging from $6,000 to $8,000 depending on size—demonstrating a clear return on investment even at limited scale.
Interoperability and the Future of Lift Data
As an emerging technology, the Vita Load Navigator does not yet operate within a formalized industry data standard. However, its design anticipates future integration into broader digital construction ecosystems.
The VLN’s onboard sensors capture extensive telemetry data, including load position, movement, weight, temperature, and operator inputs. Supported by GNSS satellite systems, this data fusion enables seamless command and control while laying the groundwork for future API-based integration.
As the construction industry continues to digitize site operations, this type of lift-level data has the potential to support real-time reporting, safety analytics, and performance benchmarking. The VLN represents an early step toward smarter, data-informed crane operations that align with the industry’s broader shift toward connected jobsites.
Establishing a New Baseline for Lifting Practices
The introduction of semi-autonomous load stabilization challenges long-standing assumptions about how crane lifts must be performed. For decades, manual taglines and spotters have been treated as unavoidable necessities, despite their inherent risks and inefficiencies.
The VLN demonstrates that this paradigm can change. By combining autonomous stabilization, GPS-based positioning, and programmable lift paths, the technology enables safer, faster, and more consistent lifts—particularly in constrained or elevated environments.
For contractors facing increasing pressure to improve safety performance while delivering projects faster and at lower cost, this approach offers a scalable alternative to traditional methods. It encourages the industry to rethink lifting protocols not as fixed practices, but as candidates for innovation
Economic Value Beyond a Single Project
While the McCarrons trial provides a clear case-level business case, the broader economic implications are equally significant. Improved crane efficiency accelerates project delivery, reduces downtime, and lowers labor costs—benefits that compound across large infrastructure programs.
Widespread adoption of technologies like the VLN could contribute meaningfully to national productivity gains, particularly as construction teams contend with labor shortages and tighter schedules. Reduced injury rates also translate into lower insurance costs, fewer disruptions, and long-term savings for employers and public systems alike.
As deployment expands, the VLN also supports job creation in advanced manufacturing, equipment servicing, and training—introducing new skill pathways aligned with technology-enabled construction.
Safer Jobsites, Smarter Industry
Beyond economics, the Vita Load Navigator points toward a more humane and sustainable construction industry. By removing workers from hazardous positions near suspended loads, it directly improves jobsite safety and reduces the physical toll associated with traditional lifting practices.
Greater precision also minimizes rework, material waste, and unnecessary crane runtime, contributing to lower emissions and more efficient resource use. These gains align with growing expectations for sustainability and responsible infrastructure delivery.
A Turning Point for Crane Operations
The partnership between PCL Construction and Vita Industrial at the McCarrons Water Treatment Plant illustrates how targeted technological innovation can address some of construction’s most persistent risks. By reimagining load control as a semi-autonomous, data-driven system, the project achieved measurable improvements in safety, productivity, and cost performance.
More importantly, it offers a glimpse of what crane operations—and construction more broadly—can become when technology is applied not as an add-on, but as a fundamental shift in how work is done. As the industry continues to build higher, tighter, and faster, solutions like the Vita Load Navigator provide a credible pathway toward safer, smarter, and more resilient project delivery.